Skip to content

Storyline · 1974–1981

Expanding the Mason Farm sewage plant, 1974–1981

In 1974 Chapel Hill chose to enlarge its Mason Farm sewage plant rather than join Durham's system. The overloaded plant forced a halt to building permits in 1976. OWASA received an EPA planning grant in 1978, and after a second federal review the EPA approved raising the plant's capacity from 5.5 to 8 million gallons a day in November 1979. In 1981 OWASA won nearly $10 million in federal and state aid, got a town permit and let contracts for the work, and the state held up sewer extensions until the plant was finished.

1974–1981 Part of Water for the towns: University Lake, the 1976–77 drought, and OWASA 10 dated events

On November 9, 1974 the Chapel Hill aldermen chose, from three engineers' plans, to enlarge the Mason Farm treatment plant, which received all of Chapel Hill's and Carrboro's treated sewage, to meet federal Environmental Protection Agency standards for Morgan Creek, rather than join Durham's Farrington Road plant; the town expected a federal grant for 85 percent of the cost and completion in 1978. In June 1976 the state Division of Environmental Management barred all building but single-family houses from tapping the town's sewer lines, and on August 16, with the plant overloaded and breaking down, the aldermen halted all building permits until September 27, limiting construction, University buildings among it, to projects permitted before July 16. By July 1978 the EPA had awarded the Orange Water and Sewer Authority $344,025 to prepare plans for enlarging the plant from 5.5 to 8 million gallons a day. In October 1979 the OWASA board learned that a new EPA review office wanted the need for the addition documented again, though the Atlanta regional office had certified the plans and OWASA had paid $350,000 for design, while developers blamed the area's strict sewer allocations for holding back apartments. On November 14 OWASA learned that the EPA had approved the expansion, about $10 million with 75 percent federal funding, to be finished by 1982; Planning Director Mike Jennings said it would let more building use town sewer lines instead of septic tanks.

By February 1981 OWASA had received almost $10 million, 75 percent from the Environmental Protection Agency and 12.5 percent from the state, toward a project of more than $11 million to rebuild the plant, raising its capacity from 5.5 to 8 million gallons a day, and to rehabilitate sewers; the work included a new administration building and a dike against Morgan Creek floods. OWASA officials had learned only weeks before that the work needed a town permit, and on April 13 the Chapel Hill Town Council approved a zoning text amendment allowing wastewater treatment plants as a special use in industrial districts and a special use permit for the expansion, on a tract of about 23 acres beside Finley Golf Course. On April 15 the OWASA board unanimously awarded four contracts: about $8 million for general construction to Dickerson Inc., $600,000 for electrical work to Bryant Durham Electric Co., $82,000 for a wastewater interceptor to Wrenn-Wilson Construction Co. and $98,000 for heating, air conditioning and plumbing to Condor Mechanical Contractors, about 12 percent under the consultants' estimate. By September the state had written OWASA restricting extensions of the sewer system until the new plant, due by July 1, 1983, was finished; OWASA chairman David Moreau said it contradicted the existing agreement. On September 17 the OWASA board approved a 13 percent water and sewer rate increase from January 1, 1982, part of a plan to cover $26 million in capital work over four years, chiefly the Cane Creek reservoir and the rebuilt treatment plant.

Towns
Chapel Hill, Morgan Creek, Carrboro, Cane Creek

The events, date by date

Every statement above comes from these dated entries in the chronology. Each links to its source.

  1. Chapel Hill aldermen choose to expand the Mason Farm sewage plant rather than join Durham At a Saturday work session the Board of Aldermen chose, from three engineers' plans, to enlarge the Mason Farm treatment plant to meet federal Environmental Protection Agency standards for Morgan Creek, which received all of Chapel Hill's and Carrboro's treated sewage. The two rejected plans would have joined Chapel Hill with Durham's Farrington Road plant; the town expected a federal grant for 85 percent of the cost and completion in 1978. Place: Mason Farm sewage plant, Chapel HillSearch the index · The Daily Tar Heel, November 11, 1974, p. 2
  2. Chapel Hill halts all building permits as its sewage plant overloads With the Mason Farm Road sewage treatment plant overloaded and breaking down, the Chapel Hill Board of Aldermen placed a moratorium on all building permits, single-family houses included, until September 27, 1976, limiting construction, University buildings among it, to projects permitted before July 16. In June the state Division of Environmental Management had already barred all building but single-family houses from tapping the town's sewer lines. Place: Chapel HillSearch the index · The Daily Tar Heel, August 27, 1976, p. 7
  3. OWASA receives an EPA grant to plan enlarging the Mason Farm sewage plant The Environmental Protection Agency awarded the Orange Water and Sewer Authority $344,025 to prepare plans and specifications for enlarging the Mason Farm Wastewater Treatment Plant from 5.5 to 8.0 million gallons a day. In the same round the Town of Chapel Hill received $302,000 more in federal community development money, bringing its block grant to $1,697,000. Place: Mason Farm Wastewater Treatment Plant, Chapel Hill · Also mentions: Orange Water and Sewer AuthorityThe Daily Tar Heel, July 13, 1978, p. 6
  4. EPA asks OWASA to re-justify its $12 million Mason Farm plant expansion The OWASA board learned that a new EPA review office wanted it to document again the need for a $12 million addition to the Mason Farm sewage plant, which would raise capacity from 5.5 to 8 million gallons a day, though the Atlanta regional office had certified the plans and OWASA had paid $350,000 for design. Developers blamed the area's strict sewer allocations for holding back apartments. Place: Mason Farm wastewater plant, Chapel HillSearch the index · The Daily Tar Heel, October 12, 1979, p. 3
  5. The EPA approves expanding the Mason Farm sewage plant The Orange Water and Sewer Authority learned that the Environmental Protection Agency had approved expanding the Mason Farm sewage treatment plant in Chapel Hill from 5.5 million to 8 million gallons a day, after a federal review that had held up construction. The project, about $10 million with 75 percent federal funding, was to be finished by 1982, and Planning Director Mike Jennings said it would let more building use town sewer lines instead of septic tanks. Place: Mason Farm sewage treatment plant, Morgan Creek, Chapel Hill · Also named: Mike Jennings · Also mentions: Orange Water and Sewer AuthorityThe Daily Tar Heel, November 16, 1979, p. 3
  6. OWASA wins nearly $10 million in federal and state aid to enlarge its wastewater plant The Orange Water and Sewer Authority received almost $10 million, 75 percent from the Environmental Protection Agency and 12.5 percent from the state, toward a project of more than $11 million to rebuild its wastewater treatment plant off Mason Farm Road, raising its capacity from 5.5 to 8 million gallons a day, and to rehabilitate sewers. OWASA took construction bids on March 24, 1981, expecting $10 million to $11 million for work that included a new administration building and a dike against Morgan Creek floods. Place: Wastewater treatment plant, Mason Farm Road, Chapel Hill · Also mentions: Orange Water and Sewer AuthorityThe Daily Tar Heel, February 20, 1981, p. 4
  7. Chapel Hill Town Council clears OWASA to enlarge the Mason Farm wastewater plant The council approved a zoning text amendment allowing wastewater treatment plants as a special use in industrial districts and a special use permit for OWASA to expand its plant on Old Mason Farm Road, beside Finley Golf Course, from 5 million to 8 million gallons a day on a tract of about 23 acres. OWASA officials said they had learned only weeks before that the work needed a town permit. Place: Mason Farm Wastewater Treatment Plant, Old Mason Farm Road, Chapel Hill · Also mentions: Finley Golf CourseThe Daily Tar Heel, April 15, 1981, p. 3
  8. OWASA lets nearly $9 million in contracts to enlarge the Mason Farm plant The OWASA board unanimously awarded four contracts for the addition: about $8 million for general construction to Dickerson Inc., $600,000 for electrical work to Bryant Durham Electric Co., $82,000 for a wastewater interceptor to Wrenn-Wilson Construction Co. and $98,000 for heating, air conditioning and plumbing to Condor Mechanical Contractors. The total ran about 12 percent under the consultants' estimate; the work was to raise capacity to 8 million gallons a day and improve treatment. Place: Mason Farm Wastewater Treatment Plant, Old Mason Farm Road, Chapel HillThe Daily Tar Heel, April 17, 1981, p. 3
  9. OWASA raises water and sewer rates 13 percent to pay for Cane Creek and a rebuilt sewage plant At its annual meeting in the Carrboro Town Hall on September 17, 1981, the OWASA board approved a 13 percent water and sewer rate increase effective January 1, 1982, part of a plan to cover $26 million in capital work over four years, chiefly the Cane Creek reservoir and rebuilding the wastewater treatment plant. A household using 1,000 gallons or less would pay $7.99 instead of $7.04, and large users 19 percent more. The board also elected Betty Sanders chair. Place: Carrboro Town Hall, Carrboro · Also named: Betty SandersThe Daily Tar Heel, September 21, 1981, p. 5
  10. The state tells OWASA to hold sewer extensions until its new treatment plant is done By September 1981 the state had written OWASA restricting extensions of the sewer system until the new wastewater plant on Mason Farm Road, due by July 1, 1983, was finished; OWASA chairman David Moreau said it contradicted the existing agreement. Place: Chapel Hill and Carrboro · Also named: David MoreauThe Daily Tar Heel, September 10, 1981, p. 3

Further reading

No indexed work is about this storyline itself yet. These are the most widely held histories of the theme it is filed under, so they may not discuss it. Follow a link to find a copy or view the material.

Background on Eno & Environment · the most widely held histories of the theme this storyline is filed under; they may not discuss it

Chapel Hill and Elisha Mitchell the Botanist

McVaugh, Rogers; McVaugh, Michael R.; Ayers, Mary · 1996

Elisha Mitchell, the University of North Carolina professor for whom Mount Mitchell is named, as botanist and as observer of early Chapel Hill, in a study by Rogers McVaugh, Michael R. McVaugh and Mary Ayers. It covers Mitchell's botanical knowledge, the plants of Chapel Hill and the town's historical geography. Published by the Botanical Garden Foundation in Chapel Hill in 1996, 122 pages with illustrations and maps.

Ribbons of Color Along the Eno River

2021

Collected first-hand and second-hand stories from the Eno River valley as told from the standpoint of African Americans and Native people who have lived along the river in Orange and Durham counties, from prehistory to the present day. Issued by the Eno River Association in Durham as volume 10, number 2 of the Eno Journal, 2021, 106 pages with illustrations.

Rogers Road

Pearce, Emily Eidenier · 2009

Emily Eidenier Pearce's history of Rogers Road, the historically African American neighborhood on the edge of Chapel Hill and Carrboro, and of what happened to it after Orange County opened its landfill next door in 1972. Drawing on interviews with residents, the book records the neighborhood's origins, family life, churches and customs, and then the environmental and social burdens of decades beside the landfill. Privately issued in 2009, 298 pages with illustrations, maps and portraits.

Dark Tales of the Eno River

Cook, David · 2025 · The History Press

David Cook collects the grim side of the Eno River's past in Orange and Durham counties: ghost stories, crimes, train wrecks and accidents, including the hanging of rebels near the river in 1771, a sawmill accident said to have started a run of hauntings, and a dance one Valentine's Day that ended badly. Published by The History Press in 2025, 141 pages with illustrations.

Johnston and Robson Mill History, New Hope Creek (Orange Co., N.C.)

Dunaway, Stewart E. · 2010

Stewart E. Dunaway's history of the two mills George Johnston built on New Hope Creek in Orange County, the first in 1793 and the second in 1820, the earlier of which he sold to the Englishman William Robson. Self-published in 2010, 256 pages with illustrations, maps and facsimiles. Topics include gristmills in Orange County and the Blackwood, Johnston, Robinson and Robson families, so the volume serves both mill history and genealogy.

Show 6 more

An Historical Address Delivered in Saint Matthew's Church, Hillsboro, N.C., on Sunday, August 24, 1924

Cheshire, Joseph Blount · 1925

Address by Bishop Joseph Blount Cheshire at St. Matthew's Church in Hillsborough on 24 August 1924, marking the parish's hundredth anniversary. Printed in Durham in 1925 at the vestry's order, with a foreword by the rector. Cheshire discusses George Micklejohn, William Mercer Green and Moses Ashley Curtis.

History of Patterson Mill, New Hope Creek, Orange County, NC

Dunaway, Stewart E. · 2010

Stewart E. Dunaway's 2010 study of Patterson Mill, a gristmill site on New Hope Creek where Orange County meets Chatham County. The book pairs a short genealogy of the Patterson family with a close survey of what remains of the mill on land now inside Duke Forest, supported by maps, facsimile documents and illustrations across 176 pages. Self-published in a second issue dated October 10, 2010.

Obstetrics and gynecology at the University of North Carolina at Chapel Hill : the first half century

2000

Departmental history of obstetrics and gynecology at the University of North Carolina at Chapel Hill covering its first fifty years, published by the department in 2000. The history covers medical schools, medical education and the teaching of obstetrics in North Carolina. First edition, xvii and 366 pages with illustrations and portraits.

A Generosity of Spirit: The Early History of the Research Triangle Park

Link, Albert N. · 1995 · Research Triangle Foundation of North Carolina

Albert N. Link's early history of Research Triangle Park, published in 1995 by the Research Triangle Foundation of North Carolina. Topics include research parks, research institutes and industrial research in the state, with the park's own history at the center. 149 pages with illustrations and maps.

Eno: Reflections on Eno River State Park

McIntyre, Michael · 1993

Michael McIntyre's 23-minute documentary video on the Eno River and Eno River State Park, produced in Durham in 1993 with support from the Duke University Institute of the Arts. It covers the river's past, its geology and the effort to preserve it, including the Indigenous peoples of the Eno River region. The container credits it with the 1993 Hal Kammerer Film and Video Award at Duke. VHS videocassette, color with sound.

Early Quakers in the Eno River Valley

Engstrom, Mary Claire · 1989 · Association for the Preservation of the Eno River Valley

Mary Claire Engstrom's history of the Quaker settlers of the Eno River valley from about 1750 to 1847, in the country that is now Orange and Durham counties. Published by the Association for the Preservation of the Eno River Valley in Durham in 1989, 73 pages with illustrations, maps and portraits.

Research this storyline

Each dated event above names its source, the place to start. For finding more on an event across newspapers, records and histories, see the research guide Follow an event across several accounts. Ask at the North Carolina Room of the Orange County Public Library for help with local sources.

Cite or share

Friends of the Orange County Public Library. “Expanding the Mason Farm sewage plant, 1974–1981.” Orange County Indexed, https://focplnc.org/orange-county-books/storylines/mason-farm-expansion-storyline-1974/. Accessed October 22, 2026.

How to cite what you find

Suggest a correction or a source →

See these events in the full chronology All storylines

Two mice reading back to back against a leaf, with the hand-lettered words Friends of the Orange County Public Library
Illustration by Caldecott Medalist Matthew Cordell, gifted to the Friends 2026